在安装预算里,我看到了oh rate,请问是什么意思?
我还看到下面一个公式OH RATE * LABOR TOTAL = OH TOTAL
1条评论...
最佳答案 最佳答案 此答案由提问者自己选择,并不代表爱问知识人的观点
揪错评论 举报

jeasonlee

[新手] 向jeasonlee提问
overhead rate
labor是劳工的意思
总体就是每个劳工的管理费用或经理费用*劳工总数=费用总数
附送一片怎样通过OH RATE计算间接成本的

How to calculate Indirect Costs using the Overhead Rate:

1. For the first year of your project, calculate the sum of all of the following budget items:

* All salaries and wages
* All fringe benefits
* All materials and supplies being purchased
* All services
* All travel
* All subgrants and subcontracts less than $25,000 each. [If you have subgrants or subcontracts that are larger than $25,000, don't include the portion(s) over that $25,000 limit.]

2. The sum you get is called the "Total Direct Cost."

3. Now multiply the Total Direct Cost by the appropriate Overhead Rate. For example, if you are performing all research on campus for an academic department such as Chemistry, you'll use 39.8% as your Overhead Rate.

4. If your project will continue beyond one year, you must repeat this calculation for each separate year.
回答:2007-06-27 16:22
提问者对答案的评价:
其它回答 共1条回答
评论 举报
回答logo

~风行雪*~

[新手] 向~风行雪*~提问
OH 率* 辛苦共计= OH 共计
回答:2007-06-19 14:56
欢迎登录知识人
会员名:

密 码:
记住我的登录状态
·新浪会员请直接登录
© 2010 Sina.com 免责声明